Glyndebourne Opera House in East Sussex has a new control system for its three electrical bridges, supplied and installed by Suffolk-based AVW Controls. The system, an upgrade of that installed seven years ago, provides Glyndebourne with absolute control of the bridges, each of which weighs seven tonnes and is capable of lifting 2.5 tonnes. Rather than disrupt the production schedule, the work was completed during the first two weeks of December 2000, while the Opera was on tour. The upgrade was the second phase of a contract originally undertaken by AVW as a sub-contractor to the erstwhile Glantre Engineering, the first phase of which involved upgrade work on the bridges themselves. Following Glantre’s demise, Glyndebourne contacted AVW direct, and is very pleased with the results. Dave Locker, production manager, said: "We are absolutely delighted with the new control system which AVW has supplied and installed. Being easy to use, staff have been able to assimilate the new system quickly, reducing the amount of time needed for training."

Latest Issue. . .

Save
Cookies user preferences
We use cookies to ensure you to get the best experience on our website. If you decline the use of cookies, this website may not function as expected.
Accept all
Decline all
Analytics
Tools used to analyze the data to measure the effectiveness of a website and to understand how it works.
Google Analytics
Accept
Decline
Advertisement
If you accept, the ads on the page will be adapted to your preferences.
Google Ad
Accept
Decline