The project is managed by David Taylor (pictured) from the Connecticut office of TPC, but George Ellerington of the London wing of Theatre Projects provided the unique theatre equipment package with an array of stage lifts, acoustics banners, hundreds of reverb chamber doors and a 40-ton three-piece canopy, all controlled from a custom PC-based memory system.
The concrete is complete to auditorium level in the concert hall and, to stabilise the building, the attic floor overhead is being poured at present. Despite the difficulties in construction over the summer, the site is being considered for an OSHA safety award. The second performance space, a 550-seat recital theatre is also underway. In this space, the entire auditorium floor can drop on a lift to give a flat floor. A 75ft diameter revolving stage allows for quick change around between a recital hall with a solid end wall and a full-flown dance and drama proscenium theatre. The Kimmel Center for the Performing Arts completes in December of 2001.