Although the show's total weight does not exceed the limits of the Hippodrome, most of the weight is concentrated in the downstage area, necessitating the strengthening of the four roof truss bays to enable each one to take the full weight at any one time. This meant each bay had to be capable of carrying 30 tonnes, the theatre's existing evenly distributed show load.
Using eight tonnes of steel, Unusual Rigging worked with Sheetfabs to fabricate 15m x 1.5m of strengthening truss for each of the four roof truss bays, and completed the install in just 10 days. The team also strengthened the upright truss stage left and right, and installed two crash decks in a single day.
(Jim Evans)