The aluminium system can made longer or shorter, narrower or made even wider by adding or removing modules. The system boasts just five components including ramp and balustrade modules and all components are in sections, which are easy to handle, and fit together in minutes, says the company.
The two level Disabled Riser sited in the main arena, from concept to installation took just six weeks, and was in place just in time for Bon Jovi to perform marking the 02's opening on 24 June.
The modular aluminium structure can be moved simply by dividing into sections, unplugging the handrail, and stored in a minimal space when the arena is required for other reasons such as an Ice Rink.
The Indigo venue disability viewing riser will be of the same general design although be a semi circular shape. The 02 has also taken on board Ra'alloys tried and trusted truck loading ramps.
(Jim Evans)